Start: January 21, 2009
Finish: March 19, 2009
Report Date: March 19, 2009

Gantt Chart

Week 5, 2009 Week 6, 2009 Week 7, 2009 Week 8, 2009 Week 9, 2009 Week 10, 2009 Week 11, 2009
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Tasks

WBS Name Start Finish Work Priority Complete Cost
1 Requirements Analysis Jan 22 Feb 6 18d
1.1 Meet with Customer Jan 22 Jan 22 1d 100%
1.2 Document Requirements Jan 23 Jan 30 6d 99%
1.3 Create Prototype Jan 23 Jan 30 6d 100%
1.4 Review with Customer Feb 2 Feb 6 5d 100%
2 Requirements Specification Feb 2 Feb 27 19d 5h
2.1 Glossary of symbols, macros, definitions, etc. Feb 2 Feb 6 4d 5h 100%
2.2 Document specifications Feb 9 Feb 17 7d 100%
2.3 Informal review, edit of SRS Feb 18 Feb 20 3d 100%
2.4 Formal review of SRS Feb 23 Feb 27 5d 100%
2.5 SRS signed-off Feb 27 Feb 27
3 Chess Engine Mar 2 Mar 12 9d
3.1 Implement chess engine Mar 2 Mar 12 9d 100%
3.2 chess engine signed-off Mar 12 Mar 12
4 User Interface Mar 2 Mar 12 8d 4h
4.1 Implement user interface Mar 2 Mar 12 8d 4h 100%
4.2 User interface signed-off Mar 12 Mar 12
5 Save/Load Game Mar 2 Mar 12 8d 2h
5.1 Implement save/load game Mar 2 Mar 12 8d 2h 100%
5.2 Save/load game signed off Mar 12 Mar 12
6 Pieces/Rules Mar 2 Mar 11 8d
6.1 Implement pieces/rules Mar 2 Mar 11 8d 100%
6.2 Pieces/rules signed off Mar 11 Mar 11
7 Assemble components Mar 13 Mar 19 5d
7.1 Assemble components Mar 13 Mar 19 5d 100%
7.2 Final product signoff Mar 19 Mar 19

Resources

Name Short name Type Group Email Cost
Ian Yoder Ian Work iay22@drexel.edu 0
Jeff Segall Jeff Work js572@drexel.edu 0
Josh Zenker Josh Work jlz27@drexel.edu 0
Vito Salerno Vito Work vs75@drexel.edu 0